Projects

Completed Projects

We have completed more than 30 lacs sqm of reinforced soil wall work, the list of some projects has been shown below.

Sr. No Projects Name Maximum Height of RS Wall(mtr) Quantity(sq mtr) Completion Year Client
1 Four laning of Gagalheri-Saharanpur-Yamunanagar (UP/Haryana border) section of NH-73 from km 33.000 (design chainage km 35.400) to km. 71.640 (design chainage km. 86.855) in the state of Uttar Pradesh under NHDP-IV on Hybrid Annuity Mode. 21.2 102000 2020 NHAI
2 Detail engineering & design consultancy in connection with 6-laning of Davangere-Haveri section from km. 298+556 to km 338+923 (pkg-2) of NH-48 (old – 4) in the state of Karnataka to be executed as “Hybrid Annuity Mode” on DBFOT under NHDP phase V. 10.0 83000 2020 NHAI
3 Four laning (from km. 308.550 to km. 358.500) Byrapura Challakere section of NH-150A on Hybrid Annuity Mode under Bharatmala Pariyojana in the state of Karnataka. 9.6 70150 2020 NHAI
4. Redesigning, Rehabilitation and Upgradation to four lane configuration & strengthening of Rohna/Hassangarh to Jhajjar section from km. 44.800 to km. 80.250 (design chainage) length 35.450 km of NH-334B in the state of Haryana on Hybrid Annuity Mode. 13.6 69000 2020 NHAI
5. Construction of RS wall including design & materials supply for Lucknow Outer Ring Road project pkg-3B1 in state of UP. 13.0 105000 2019 NHAI
6. Construction of RS wall including design & materials supply at Delhi-Meerut expressway pkg-1 section of NH-24 in state of Delhi. 12.8 53000 2018 NHAI
7. Construction of RS wall including design & material supply for VUPs, flyovers for Varanasi Ring road project in state of UP. 14.0 38000 2018 NHAI
8. Construction of RS wall including design & materials supply at Hissar-Dabwali pkg-2 section of NH-10 in state of Haryana. 13.5 63000 2017 NHAI
9. Construction of RS wall including design & material supply at Hissar Dabwali pkg-1 section of NH-10 in state of Haryana. 12.0 43000 2017 NHAI
10. Construction of RS wall for 4 laning of Rohtak to Hissar section of NH-10 from km. 87.0 to km. 170.00 including connecting link from km. 87.00. 13.5 50000 2015 NHAI
Apart from listed above we have completed no. of Reinforced Soil wall projects and other geosynthetic works.